obras.fep.up.pt https://obras.fep.up.pt/en Obras FEP Wed, 05 Dec 2018 17:00:23 +0000 en-US hourly 1 The Obelisk started to be repaired https://obras.fep.up.pt/en/2018/11/30/inicio-dos-trabalhos-do-obelisco/ Fri, 30 Nov 2018 19:38:07 +0000 https://obras.fep.up.pt/?p=884 The obelisk requalification works started today. The intervention will allow the rehabilitation of the sculpture of José Rodrigues.

]]>
Concrete slabs removed https://obras.fep.up.pt/en/2018/11/27/placas-de-betao-retiradas/ Tue, 27 Nov 2018 19:30:46 +0000 https://obras.fep.up.pt/?p=878

The façade of FEP main building began to be intervened with the removal of the concrete slabs that will be replaced. The rest will be rehabilitated.

 

]]>
The auditorium 215 already has new structures https://obras.fep.up.pt/en/2018/11/05/o-anfiteatro-215-ja-tem-novas-estruturas/ Mon, 05 Nov 2018 19:25:51 +0000 https://obras.fep.up.pt/?p=872 The new structures for the chairs have already begun to be built in the auditorium 215 which will have fewer but bigger seats and more circulation space.

]]>
New window frames https://obras.fep.up.pt/en/2018/10/11/chegada-das-novas-caixilharias-da-fep/ Thu, 11 Oct 2018 10:02:05 +0000 https://obras.fep.up.pt/?p=819 The new window frames have already begun to be renovated and placed in the Library. Afterward, the painting will be done in black.

]]>
Rehabilitation of Professor´s offices https://obras.fep.up.pt/en/2018/10/10/reabilitacao-dos-gabinetes-dos-docentes/ Wed, 10 Oct 2018 09:55:08 +0000 https://obras.fep.up.pt/?p=814 The professor’s offices have already begun to be changed through painting and rehabilitation.

]]>
Painting of the radiators https://obras.fep.up.pt/en/2018/10/01/pintura-dos-radiadores/ Mon, 01 Oct 2018 09:00:58 +0000 https://obras.fep.up.pt/?p=808 The radiators recovery and painting works are already underway. The radiators will be painted in their original color.

]]>
Recovery of verandahs https://obras.fep.up.pt/en/2018/09/10/recuperacao-das-palas-das-varandas/ Mon, 10 Sep 2018 08:58:01 +0000 https://obras.fep.up.pt/?p=799 The vanes of the balconies of the canteen’s facade are already being recovered.

]]>
Climatization of the Noble Hall https://obras.fep.up.pt/en/2018/09/03/climatizacao-do-salao-nobre/ Mon, 03 Sep 2018 08:52:07 +0000 https://obras.fep.up.pt/?p=795 The works to prepare the infrastructures for the air conditioning equipment of the Noble Hall are already underway.

]]>
Cleaning of the exterior walls https://obras.fep.up.pt/en/2018/06/04/limpeza-da-fachada/ Mon, 04 Jun 2018 13:39:32 +0000 https://obras.fep.up.pt/?p=781 The cleaning of the exterior walls is in progress. This is an operation that precedes the repair of the concrete.

]]>
Bar in temporary facilities already has a terrace https://obras.fep.up.pt/en/2018/05/14/a-esplanada-do-bar-da-fep-ja-esta-operacional/ Mon, 14 May 2018 10:54:23 +0000 https://obras.fep.up.pt/?p=158 Thanks to AEFEP, the bar has now a terrace that allows FEP’s community to enjoy the good weather.

]]>
The floor of the entrance hall has been removed https://obras.fep.up.pt/en/2018/05/02/pavimento-do-hall-de-entrada-foi-retirado/ Wed, 02 May 2018 17:04:14 +0000 https://obras.fep.up.pt/?p=519 Some parts of the floor in the lobby were removed to replace the hidden pipes.

]]>
The replacement of the infrastructures has begun https://obras.fep.up.pt/en/2018/04/02/intervencao-no-piso-3/ Mon, 02 Apr 2018 17:00:47 +0000 https://obras.fep.up.pt/?p=525 One of the most important components of the work in progress is the replacement of all the infrastructures (electrical, computer, water, heating and ventilation). It is a replacement that is essential to ensure the proper functioning of the school. The replacement of these networks has already begun on the 3rd floor.

]]>
The sanitary facilities are ready for renovation https://obras.fep.up.pt/en/2018/02/26/as-instalacoes-sanitarias-estao-prontas-para-a-renovacao/ Mon, 26 Feb 2018 14:53:21 +0000 https://obras.fep.up.pt/?p=569 All the cabins have been demolished to allow the reconstruction of the toilets.

]]>
Room 260 is again a flat room https://obras.fep.up.pt/en/2018/02/05/a-sala-260-volta-a-ser-uma-sala-plana/ Mon, 05 Feb 2018 15:01:33 +0000 https://obras.fep.up.pt/?p=572 The metal structure that supported the room 260 has already been dismantled.

]]>
Old new rooms 163 and 165 https://obras.fep.up.pt/en/2018/02/01/novas-velhas-salas-162-163-e-165/ Thu, 01 Feb 2018 15:07:04 +0000 https://obras.fep.up.pt/?p=579 After the removal of the partition walls, which allowed to accommodate in these spaces the AEFEP, Skills Academy, FEP Junior Consulting and e-Copy, the rooms 163 and 165 return to their previous configuration.

]]>
The auditorium renovation has started https://obras.fep.up.pt/en/2018/01/30/avanca-a-renovacao-dos-anfiteatros/ Tue, 30 Jan 2018 15:18:26 +0000 https://obras.fep.up.pt/?p=582 After the hooves, the chairs were also removed. The auditoriums are ready to receive the new infrastructures.

]]>
The new auditoriums are being shaped https://obras.fep.up.pt/en/2018/01/15/inicio-da-restruturacao-dos-anfiteatros/ Mon, 15 Jan 2018 19:38:48 +0000 https://obras.fep.up.pt/?p=294 The chairs and tables of all the auditoriums are being removed. This is probably the most visible face of the building rehabilitation. At the end of the renovation, the auditoriums will be unrecognizable and much more functional and comfortable.

]]>
D of demolition https://obras.fep.up.pt/en/2018/01/04/comecam-as-obras-no-edificio-principal/ Thu, 04 Jan 2018 19:36:02 +0000 https://obras.fep.up.pt/?p=288 The work started by the demolition of partitions walls of offices, services, and student spaces, which have been installed over time. Also, the sanitary facilities and auditoriums will be demolished and subsequently renovated.

]]>
The building is almost empty https://obras.fep.up.pt/en/2018/01/03/o-edificio-esta-quase-desocupado/ Wed, 03 Jan 2018 09:10:05 +0000 https://obras.fep.up.pt/?p=560

Almost all of the furniture and equipment has already been removed from the building. Some spaces are unrecognizable. This is the case of the Grand Hall.

]]>
Classes restart https://obras.fep.up.pt/en/2018/01/02/mudanca-para-as-instalacoes-temporarias/ Tue, 02 Jan 2018 19:27:13 +0000 https://obras.fep.up.pt/?p=279

After the Christmas holidays, academic activities restarted, now in the temporary facilities.

]]>
Work in progress https://obras.fep.up.pt/en/2017/12/27/a-mudanca-esta-em-curso/ Wed, 27 Dec 2017 09:09:03 +0000 https://obras.fep.up.pt/?p=708 After months of planning, the move progresses as planned. The building is empty. This process of moving will be repeated a year from now.

]]>
Tapestry has already been removed https://obras.fep.up.pt/en/2017/12/20/tapecaria-ja-foi-retirada/ Wed, 20 Dec 2017 10:59:06 +0000 https://obras.fep.up.pt/?p=717 The Tapestry that occupied one of the walls of the Scientific Council room has already been removed. The Tapestry, by Master Júlio Resende, will be followed for restoration during the period of works.

]]>
FEP is closed for renovation https://obras.fep.up.pt/en/2017/12/16/encerramento-do-edificio-principal/ Sat, 16 Dec 2017 14:11:39 +0000 https://obras.fep.up.pt/?p=96 For reasons of works and relocation of facilities, the access to FEP’s main building will be forbidden on December 15.

 

]]>
The last public event before temporary closing https://obras.fep.up.pt/en/2017/12/15/ultimo-evento-antes-do-encerramento-temporario/ Fri, 15 Dec 2017 15:28:15 +0000 https://obras.fep.up.pt/?p=113 Read more about The last public event before temporary closing[…]]]> The tribute to Professor António Almodovar (1953-2016) was the last event to be held in the main building of FEP before the temporary closing of the facilities.

The library, already without tables, shelves, and books, was the place chosen to hold this event. The tribute was intended to remember the academic and personal journey of Professor António Almodovar.

]]>
The library reopens in the post-graduation building https://obras.fep.up.pt/en/2017/11/16/a-biblioteca-ja-se-encontra-a-funcionar-no-edificio-das-pos-graduacoes/ Thu, 16 Nov 2017 14:05:23 +0000 https://obras.fep.up.pt/?p=87 The Library is already open in the post-graduation building (room 505). Due to the limited space, there is only a small reading space, however, all services are available.

]]>
The installation of the monoblocks has began https://obras.fep.up.pt/en/2017/11/10/inicio-da-preparacao-das-instalacoes-temporarias/ Fri, 10 Nov 2017 19:19:08 +0000 https://obras.fep.up.pt/?p=272 Today, the first monoblocs began to be installed in the parking lot. The 238 monoblocks will hold the major part of the school’s activity during the works.

]]>